Queenstown Terminal Upgrade
The $21 million upgrade of the Queenstown Airport Terminal has made excellent progress with Stage 1 now complete and Stage 2 due for completion at the end of June in time for the busy ski season, Queenstown Lakes District Mayor Clive Geddes said.
Stages 1 and 2 incorporate the final forecourt layout and passenger arrival pick up and departure set down area.
Remaining Stages 3 and 4 (landside layout) had now been approved for construction by the Council.
“It’s a credit to the Queenstown Airport Corporation and project managers Arrow International that this project has been delivered to date, both on time and under budget,” Mr Geddes said.
Projected expenditure for the remaining Stages 3 and 4 was $11 million dollars with Stage 3 programmed for completion in mid November and Stage 4 in March 2007.
“I consider that the completed landscaping and traffic control will complete the transition of this terminal into one of the most attractive airport entry and departure points in New Zealand,” Mr Geddes said.
Landside works for Stages 3 and 4 include:
- New bus pick-up area.
- Ring road and round-about at Lucas Place (to be completed December 2006).
Browse by Date
- March 2012
- December 2011
- November 2011
- September 2011
- August 2011
- July 2011
- June 2011
- May 2011
- April 2011
- February 2011
- January 2011
- December 2010
- November 2010
- October 2010
- September 2010
- August 2010
- July 2010
- June 2010
- May 2010
- April 2010
- December 2009
- October 2009
- September 2009
- August 2009
- July 2009
- June 2009
- March 2007
- February 2007
- November 2006
- June 2006
- May 2006
- April 2006
- March 2006
- February 2006
- January 2006
- December 2005
- November 2005
- October 2005
- September 2005